CDBG-DR MHP 2023/2024
| Milestone | Date |
|---|---|
| NOFA Release | September 8, 2025 |
| NOFA Workshop (General Population) | September 23, 2025 |
| NOFA Workshop (Tribal Entities) | September 24, 2025 |
| Application Release | October 10, 2025 |
| Application Due Date | November 21, 2025 |
| Award Announcements | February 2026 |
DR-ACCEL program
| Milestone | Date |
|---|---|
| Project Solicitation Release | January 31, 2025 |
| Application Release | February 20, 2025 |
| Application Due Date | March 26, 2025 |
| Awards Announcements | August 2025 |
| Standard Agreement Execution | November 2025 |
| Commencement of Construction | February 2026 |
| Construction End | February 2029 (3 Years) |
| Lease-Up | May 2029 |
| Permanent Conversion | August 2029 |
| Project Closeout | October 2029 |
| DR23 Grant Closeout | July 15, 2030 |
DR-MHP 2020 Program
| Milestone | Date |
|---|---|
| DR-MHP NOFA Release | June 28, 2024 |
| Workshops | July 11, 2024 (general population) July 15, 2024 (tribal applicants) |
| DR-MHP Application Release | July 19, 2024 |
| DR-MHP Application Due Date | September 6, 2024 |
| DR-MHP Award Announcements | March 18, 2025 |
| DR-MHP Funds encumbered through an executed Standard Agreement | March, 2025 through August, 2025 |
| Project Construction Start | March 29, 2026 |
| Project Construction Completion | September 25, 2027 |
| Project Lease Up | December 24, 2027 |
| Project Closeout Date | June 21, 2028 |
| Grant Period Close | September 16, 2028 |
DR-MHP 2018 Program
| Milestone | Date |
|---|---|
| Publish Program Policies and Procedures | Mid-January 2021 |
| Begin Accepting Due Diligences via Grant Network | January 15, 2021 |
| Q&A Webinar on Policies and Procedures | January 28, 2021 |
| Due Diligence Submissions due in Grants Network | March 15, 2021 |
| Final Date to Submit Solicitation for HCD Review | 6 months after MSA Execution |
| Final Date to Submit Project Applications | December 31, 2022 |
| Final Date to HCD to issue Notice(s) to Proceed | December 31, 2025 |
| Final Date to Submit Certificate of Occupancy for all Projects | January 31, 2029 |
| HCD DR_MHP Program Closeout | December 1, 2029 |
| HCD-HUD Grant Closeout | December 1, 2030 |
DR-MHP 2017 Program
| Milestone | Date |
|---|---|
| Final Date to Submit Notice of Interest | January 31, 2020 |
| Publish Program Policies and Procedures | March 31, 2020 |
| Q&A Webinar on Policies and Procedures | March 25, 2020 |
| Open Program Portal via Grants Network | March 27, 2020 |
| Due Diligence Submission due in Grants Network | August 1, 2020 |
| Begin Master Standard Agreement (MSA) Execution Process in Grants Network | Week of August 17, 2020 |
| Final Date to Submit Solicitation for HCD Review | 6 months after MSA Execution |
| Policies and Procedures Version 2 Workshop (webinar) | September 22, 2020 |
| Application Workshops (webinar) | October 2020 |
| Final Date to Submit Project Applications | December 31, 2021 |
| HCD Reallocation of Unused Funds | January 2022 |
| Final Date for HCD to issue Notice(s) to Proceed | December 31, 2025 |
| Final Date to Submit Certificate of Occupancy for all Projects | December 31, 2027 |
| HCD DR-MHP Program Closeout | January 31, 2027 |