PRP Round 2 Timeline

Application materials for the PRP NOFA must be submitted electronically via the application portal on the Department’s website by the date specified in the table below. The Application period for this NOFA has closed.

 Timeline
2023 NOFA ReleaseDecember 28, 2023
Application ReleaseJanuary 11, 2024
Application OTC Period BeginsMarch 28, 2024

Deadline for Set-Aside Applications

  • Small Project
  • Residential Hotel
  • Foreclosure
April 29, 2024, 4:00 PM
Deadline for General Pool ApplicantsMay 28, 2024, 4:00 PM
Awards AnnouncementContinuously as applications are approved, approximately 4-5 months after application submittal, but no later than December 31, 2024
Funds encumbered through an executed Standard AgreementNo later than December 31, 2025
Capitalized Operating Subsidy Reserve expenditure deadlineDecember 31, 2028